Project Name: SKF Bearing production line

End user: SKF (Dalian) bearing and precision technology products Co., Ltd

Project time: from 2014 to now

Project Description:

Provide SKF Bearing with multiple turnkey projects of automatic intelligent production line. The mixed line production of various types of products is realized, the capacity improvement space is reasonably planned, and the connection operation of equipment in each area is stable. The application of patent pushing mechanism can reduce the safe line stopping rate, and a number of mechanical and material data analysis can ensure the stability and reliability of equipment operation.

The project reasonably applies the production line planning of three-dimensional space, carries out the overall production line 3D planning and design, functional analysis, equipment manufacturing, on-site installation and commissioning, and automatic operation and delivery in combination with manufacturing equipment. The equipment is equipped with patented products such as magnetic coupling, plate chain conveyor line, roller line, turntable, elevator, stop assembly mechanism, compatible claw of multi model products, loading and unloading mechanism, etc.


Time

Entry name

2016.5

SKF Dalian production line connection project

2018.10

SKF Dalian automatic intelligent production line project

2019.6

SKF Beijing  automatic intelligent production line project

2020.2

SKF Dalian  conveyor line project



Project Name: Hangzhou Kalai composite film coating process workstation project

Time: October 2020

Project introduction:

We have provided the film covering process workstation for Hangzhou Kalai., According to the customer's technological process and needs, the use of three-dimensional space for reasonable production line planning, combined with manufacturing tools for three-dimensional planning and design, functional analysis, equipment manufacturing, on-site installation and debugging, automatic operation as one of the turnkey project. The project equipment includes seven axis robot, coating table heating equipment, roller bed conveying equipment, feeding trolley and gripper, etc.


Time

Entry name

2020.10

Hangzhou Kalai film mulching process workstation project